RMT Energy | Construction
RMT Inc.

Buffalo Mountain Wind Farm

Invenergy Wind

INTERCONNECTING UTILITY:

Tennessee Valley Authority

RMT'S ROLE:

  • Engineer and general contractor for electrical system
  • 34.5 kV collector system
  • 34.5/161 kV substation
  • Fiber optic communications

PROJECT HIGHLIGHTS:

  • Built site on Coal Creek Mountain, a former strip mining site
  • Hired local mining labor with knowledge and experience to complete the project with no personal injuries
  • Facilitated development of helicopter landing area to provide emergency help at top of mountain
  • Provided ongoing energy, environmental, and economic benefits:
  • Generates enough electricity to power approximately 7,991 homes annually
  • Offsets the combustion of approximately 36,925 tons of coal per year, which reduces the equivalent of 4,860 tons of CO2 emissions to the atmosphere annually
  • Provides income to local landowners through annual lease payments

QUICK FACTS:

Oliver Springs, Tennessee
27 MW
15 Vestas V80 1.8-MW
Turbines